Judgments

Decision Information

Decision Content

A-919-91
Thomas Fuller Construction Co., (1958) Limited
(Plaintiff) (Appellant)
v.
Her Majesty the Queen in Right of Canada
(Defendant) (Respondent)
INDEXED AS: THOMAS FULLER CONSTRUCTION Co, (1958) LTD. V. CANADA (CA.)
Court of Appeal, Marceau J.A.—Ottawa, October 6, 1992.
Contracts — Contractor suing Crown for damages caused by delays of two construction projects — Agreements purport ing to authorize contractor to sue on behalf of subcontractors
— Appeal from Trial Division order finding litigation agree ments invalid as offending laws of champerty and maintenance
— Trial Judge not properly seized of matter as Crown's motions not supported by Court Rules — Order purposeless in that, even if agreements declared null and void, contractor could still contend that liable under own contract with subcon tractors — Leave to amend also useless as no amendment now required — Appeal allowed.
STATUTES AND REGULATIONS JUDICIALLY CONSIDERED
Federal Court Rules, C.R.C., c. 663, RR. 341(b), 419(1), 474(1)(a).
CASES JUDICIALLY CONSIDERED
REFERRED TO:
Flexi-Coil Ltd. v. F.P. Bourgault Industries Air Seeder Division Ltd. (1991), 35 C.P.R. (3d) 154; 123 N.R. 235 (F.C.A.); Bemeche v. Canada, [1991] 3 F.C. 383; (1991), 133 N.R. 232 (C.A.).
APPEAL from Trial Division order ([1992] 1 F.C. 512) declaring litigation agreements between contrac tor and subcontractors invalid as offending laws of champerty and maintenance. Appeal allowed.
COUNSEL:
P. Donald Rasmussen and Ernest S. J. Schmidt for plaintiff (appellant).
J. Grant Sinclair, Q.C. and Robert P. Hynes for defendant (respondent).
SOLICITORS:
Rasmussen, Starr & Ruddy, Ottawa, for plaintiff (appellant).
J. Grant Sinclair, Q.C., Toronto, and Deputy Attorney General of Canada for defendant (respondent).
The following are the reasons for judgment of the Court delivered orally in English by
MARCEAU J.A.: We are all of the view that the order of the Trial Division [[1992] 1 F.C. 512] under attack in this appeal cannot be allowed to stand.
Two different motions are disposed of by the order, each one relating to a separate action. These two actions brought by Thomas Fuller Construction against the Crown are in respect of two distinct con struction contracts. Fuller claims compensation under each contract for damages suffered by it as a result of delays caused by the Crown. In the course of the examination for discovery, it was revealed that a por tion of the damages claimed in each action related to losses sustained by Fuller' s subcontractors resulting from the same delays. It came to light that, prior to launching its actions, Fuller signed agreements with a number of its subcontractors. Under the agreements, Fuller acknowledged the validity of the subcontrac tors' claims and agreed to pursue an action against the Crown in excess of, but including, the amount of the subcontractors' claims set out in the agreements. The subcontractors agreed to provide evidence and assistance to Fuller in its prosecution and to pay a proportionate share of the costs of the action. In addi tion, the subcontractors agreed to accept, in full satis faction of any claim which they might have against Fuller, the amount recovered by Fuller in respect of these damages in Fuller' s action against the Crown. The agreements also provide for division of a suc cessful judgment if the allocation is not clear from the judgment, and for dealing with a contingency
offer for settlement which is accepted by some but not all of the claimants.
The Crown brought a motion in action T-1416-87 for an order that the so-called litigation agreements that Fuller had entered into with its subcontractors be declared void and struck down as offending the laws of maintenance and champerty. The Crown brought a motion in action T-1036-87 for an order for judgment dismissing the part of Fuller's claim against the Crown relating to the losses sustained by the subcon tractors. In both motions, there was also a request for leave to amend the statement of defence so as to plead nullity of the agreements if the main relief sought were refused.
By order of the Associate Chief Justice, the two motions were consolidated and submitted together for adjudication. They were then disposed of by a single order. This is, of course, the order under appeal. By this order, the learned Trial Judge determined first that Fuller could not assert as its own claims of its subcontractors against the Crown, in the absence of privity or liability between the subcontractors and the Crown; he then addressed the litigation agreements and found that they were tantamount to assignments of a bare right to sue which offend the laws of cham- perty and maintenance. The conclusion was that these agreements were invalid.
We are of the view that the Trial Judge could not make the order that he made first because he was not properly seized of the question of law that he pur ported to determine and second because his determi nation was purposeless.
The Judge was not properly seized of the matter because the two motions were not supported by any rule of the Court. Rule 474(1)(a) [Federal Court Rules, C.R.C., c. 663] which permits the Court to determine a preliminary question of law relevant to the decision of the matter was not applicable since
the validity of the "litigation agreements", the ques tion of law seen by the Judge, was, in no way, raised by the pleadings and, in any event, could not be seen as a pure question of law based on undisputed facts the resolution of which would eliminate the need for a trial or a substantial part of it (see the judgment of this Court in Berneche v. Canada, [1991] 3 F.C. 383). Rule 419(1) which permits the Court to strike out all or part of a pleading obviously did not apply either since there was no allegation in the statement of claim to strike. And Rule 341(b) which allows for judgment of any matter in respect of which the only evidence consists of documents, was no more appli cable, the Court having held over and over again that it is necessary for a determination under that Rule that no relevant facts be in controversy and the law be so clear that there would be no need for a trial (see Flexi-Coil Ltd. v. F.P. Bourgault Industries Air Seeder Division Ltd. (1991), 35 C.P.R. (3d) 154 (F.C.A.)).
As for the lack of purpose in the order, suffice it to say that even if the "litigation agreements" are declared null and void, this will not prevent Fuller from contending that it is liable under its own con tract with the subcontractors and that liability entails a certain amount of loss to Fuller. Whether or not such contention will be successful or even receivable in the factual circumstances of the case is not a mat ter before this Court at this time.
We have no difficulty agreeing with counsel for the Crown that the case is a very complex one but that is no reason to try to deal with it piece by piece and at a moment in the proceedings when the pieces are not even identified and put together.
There is finally the alternative relief sought by both motions of an order granting leave to amend. We consider, and counsel agree, that this is also use less, no amendment being required at this time.
The appeal will therefore be granted and the order of the Trial Division will be set aside. The judgment
being based on a point not raised in the factums, there shall be no order as to costs.
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.